Jalswarajya Project
Jalswarajya Project

Phase Status


Phase/BatchGPs SelectedGPs Under ProjectPlanning PhaseImplementation PhaseO&M PhaseExit Phase
Phase I
Pilot26230 7  11 5
Batch I2242100 88  115 7
Batch II4864371 290  135 11
Batch III5654950 352  140 3
Total130111651 737  401 26
Phase II
Batch I4323990 220  157 22
Batch II165814591 954  464 40
Total209018581 1174  621 62
Grand Total 3391 3023 2  1999  1022  88
In % 89.15% 0.07%  66.13%  33.81%  2.91%
Planning - GPs where 1st Istallment Not Release & Civil Work Not Started.
Implementation - Civil work started but facilities not operationalised.
Operation & Maintanance - Facilities operationalised successfully.
Exit - Completing 3-Month of O&M successfully & Exit in all Respects.
Phase Status
GPs
3391 3023 2 1999 1022 88
Selected Projected Planning Implementation O&M Exit

Phase